Rhodes and South Aegean municipalities challenge Greece’s wind farm rules

Rhodes and the South Aegean union of municipalities have filed separate challenges to Greece’s renewables plan, focusing on rules for wind farms on islands.

Wind turbines

Rhodes municipality and the Regional Union of Municipalities of the South Aegean have asked Greece’s Council of State to annul the new national spatial planning framework for renewable energy, challenging in particular its rules on where wind farms can be built on the islands.

The two authorities have filed separate applications, setting out seven grounds for annulment each. They contest provisions of the framework the Ministry of Environment and Energy approved in August 2026.

At issue is how the framework determines which sites are eligible for new turbines. The applicants say the rules give too little weight to each island’s environment and land-use needs.

The dispute over the 300 square kilometre threshold and the 4% cap

The framework treats islands differently according to their size. It generally rules out new wind installations on islands smaller than 300 square kilometres, with exceptions for certain public-interest infrastructure and for electricity system security.

Michalis Papageorgiou, the union’s legal adviser, told TOP FM journalist Rena Venianaki that the rule allows new wind farms to be considered on larger islands such as Rhodes, Karpathos, Andros and Naxos, subject to conditions.

The authorities also question the cap of 4% of the land area of each municipal unit eligible under the island rules. They argue that it does not reflect how much development individual areas can accommodate.

The union says planners should consider Natura 2000 sites, settlements, archaeological sites, existing infrastructure and the cumulative impact of wind farms.

Councils seek a greater role

The challenge also raises the question of how much say local authorities should have in energy planning.

Papageorgiou says the government gave too little weight to comments submitted by regional and local authorities during the consultation.

He says decisions about renewable energy should reflect each island’s demand for power, the grid’s capacity to absorb the electricity generated and the need to protect the natural environment.

The union’s challenge covers municipalities across the Cyclades and the Dodecanese, including Leros. The case concerns the national rules and does not relate to a specific project on Leros.

The framework was published in the Government Gazette, issue D 694 of 19 August 2026. The Council of State has yet to rule on whether the challenged provisions are lawful.